Park & Stride update
30th June 2023
You may have noticed that works on the former Green Shed site to create a ‘Park & Stride’ car park haven’t progressed in recent weeks. Stirling Council has today issued an update on works:
“A few challenges have come to light, which are prolonging the project programme. We are experiencing a delay to both the re-positioning of the lighting column on the A84 footpath (this is being progressed with BEAR Scotland) and the electrical supply connection (needed for the EV Chargers and the car park lighting).
The current estimate for full completion of these items and opening is by the end of September this year.”